Welcome to TrueTroop.

00:00:02.360 --> 00:00:02.860
I'm Paul.

00:00:03.920 --> 00:00:05.780
If project planning is new to you, this

00:00:05.840 --> 00:00:07.200
is a good place to begin.

00:00:08.120 --> 00:00:10.420
We will learn ten basic ideas using one

00:00:10.520 --> 00:00:12.660
simple example: a council building a new

00:00:12.780 --> 00:00:13.120
school.

00:00:14.160 --> 00:00:15.680
We will call it Riverside School.

00:00:16.640 --> 00:00:18.190
The school, dates and figures are

00:00:18.280 --> 00:00:19.340
teaching examples.

00:00:20.380 --> 00:00:22.280
You do not need to open any software or

00:00:22.320 --> 00:00:24.240
remember complicated calculations.

00:00:25.340 --> 00:00:27.480
Listen for what each term means, picture

00:00:27.520 --> 00:00:29.590
the example, and connect it to something

00:00:29.620 --> 00:00:30.880
you already understand.

00:00:31.900 --> 00:00:33.430
Let's start with the word project.

00:00:34.540 --> 00:00:36.340
A project is a temporary piece of work

00:00:36.400 --> 00:00:38.520
undertaken to deliver a specific, unique

00:00:38.580 --> 00:00:39.980
result.

00:00:40.040 --> 00:00:41.460
Temporary means the project has a

00:00:41.500 --> 00:00:43.500
beginning and an end.

00:00:43.560 --> 00:00:45.150
It does not mean the result is only

00:00:45.200 --> 00:00:47.500
useful for a short time.

00:00:47.600 --> 00:00:49.580
Building Riverside School is a project.

00:00:50.640 --> 00:00:52.250
The work starts with an agreed need and

00:00:52.340 --> 00:00:54.040
ends when the agreed school and handover

00:00:54.060 --> 00:00:56.320
requirements have been delivered.

00:00:56.370 --> 00:00:58.120
The building may then serve children for

00:00:58.160 --> 00:00:59.020
many years.

00:00:59.960 --> 00:01:01.560
Running lessons in the school every week

00:01:01.620 --> 00:01:03.220
is different: that is ongoing

00:01:03.280 --> 00:01:04.250
operational work.

00:01:05.400 --> 00:01:07.660
A useful question is, are we creating or

00:01:07.680 --> 00:01:09.280
changing something through a defined

00:01:09.400 --> 00:01:10.140
piece of work?

00:01:11.220 --> 00:01:13.320
If so, we may be looking at a project.

00:01:14.380 --> 00:01:15.980
Remember: a project delivers a

00:01:16.020 --> 00:01:17.120
particular result.

00:01:18.000 --> 00:01:19.960
A programme brings related projects and

00:01:20.000 --> 00:01:21.650
change activities together so they can

00:01:21.680 --> 00:01:23.940
achieve a wider benefit.

00:01:24.020 --> 00:01:25.640
Managing the work together helps the

00:01:25.680 --> 00:01:27.660
organisation coordinate decisions,

00:01:27.680 --> 00:01:29.660
resources and the changes people need to

00:01:29.760 --> 00:01:30.020
make.

00:01:31.060 --> 00:01:32.460
Imagine that the council wants to

00:01:32.520 --> 00:01:34.120
improve access to education.

00:01:35.160 --> 00:01:36.740
Building Riverside School is one

00:01:36.840 --> 00:01:37.340
project.

00:01:38.400 --> 00:01:40.260
Refurbishing two existing schools is

00:01:40.320 --> 00:01:40.680
another.

00:01:41.720 --> 00:01:43.600
Introducing a shared teaching technology

00:01:43.700 --> 00:01:44.760
system is a third.

00:01:45.780 --> 00:01:47.780
Training staff to use the new facilities

00:01:47.860 --> 00:01:49.270
also supports the change.

00:01:50.250 --> 00:01:52.160
Together, these activities could form an

00:01:52.200 --> 00:01:54.780
education improvement programme.

00:01:54.840 --> 00:01:56.640
The shared benefit is better education

00:01:56.660 --> 00:01:58.620
provision, not simply three completed

00:01:58.640 --> 00:02:00.560
construction or technology projects.

00:02:01.620 --> 00:02:03.380
In American English, this management

00:02:03.480 --> 00:02:05.120
term is usually written program.

00:02:06.160 --> 00:02:08.300
The central idea is the same: related

00:02:08.360 --> 00:02:09.550
changes managed together.

00:02:10.560 --> 00:02:12.580
A portfolio is a collection of projects

00:02:12.600 --> 00:02:14.240
and programmes managed to support an

00:02:14.360 --> 00:02:15.880
organisation's priorities.

00:02:16.920 --> 00:02:18.790
The individual investments do not all

00:02:18.790 --> 00:02:20.330
have to be related to one another.

00:02:21.360 --> 00:02:23.060
Our council may invest in better

00:02:23.080 --> 00:02:26.460
schools, safer roads and new housing.

00:02:26.540 --> 00:02:27.850
Those activities have different

00:02:27.880 --> 00:02:29.920
immediate purposes, but they all support

00:02:29.930 --> 00:02:31.450
the council's wider plans for the

00:02:31.500 --> 00:02:32.180
community.

00:02:33.060 --> 00:02:34.300
They can therefore sit within its

00:02:34.340 --> 00:02:35.600
investment portfolio.

00:02:36.620 --> 00:02:38.560
Portfolio decisions include choosing

00:02:38.620 --> 00:02:40.370
which investments to fund and balancing

00:02:40.440 --> 00:02:43.240
limited money and people across them.

00:02:43.250 --> 00:02:45.560
A portfolio is not simply a very large

00:02:45.600 --> 00:02:46.070
project.

00:02:47.140 --> 00:02:48.980
Think of it as the organisation's wider

00:02:49.020 --> 00:02:50.580
collection of chosen investments.

00:02:51.680 --> 00:02:53.540
Some projects sit within programmes.

00:02:54.600 --> 00:02:56.060
Others may sit directly within a

00:02:56.100 --> 00:02:56.860
portfolio.

00:02:57.880 --> 00:02:59.670
Let's connect those three words using

00:02:59.760 --> 00:03:00.630
Riverside School.

00:03:01.700 --> 00:03:04.220
Building the school is the project.

00:03:04.300 --> 00:03:05.930
Improving education through several

00:03:06.000 --> 00:03:07.780
related projects and changes is the

00:03:07.800 --> 00:03:09.320
programme.

00:03:09.330 --> 00:03:10.830
The council's wider collection of

00:03:10.880 --> 00:03:13.260
education, roads and housing investments

00:03:13.320 --> 00:03:15.240
is the portfolio.

00:03:15.340 --> 00:03:16.820
These are three different views of the

00:03:16.860 --> 00:03:17.180
work.

00:03:18.240 --> 00:03:20.600
At project level, the team asks, how

00:03:20.640 --> 00:03:21.810
will we deliver this school?

00:03:22.860 --> 00:03:25.290
At programme level, the team asks, how

00:03:25.300 --> 00:03:26.980
will these related changes improve

00:03:27.020 --> 00:03:28.900
education together?

00:03:28.990 --> 00:03:31.400
At portfolio level, the organisation

00:03:31.520 --> 00:03:33.720
asks, which investments best support our

00:03:33.800 --> 00:03:35.680
priorities with the resources we have?

00:03:36.720 --> 00:03:38.380
This example shows one possible

00:03:38.390 --> 00:03:39.040
arrangement.

00:03:40.120 --> 00:03:41.790
Not every project must belong to a

00:03:41.800 --> 00:03:42.310
programme.

00:03:43.420 --> 00:03:45.240
For now, remember the school, the

00:03:45.320 --> 00:03:47.300
education improvement programme, and the

00:03:47.360 --> 00:03:49.200
council investment portfolio.

00:03:50.040 --> 00:03:51.850
The project life cycle is the set of

00:03:51.940 --> 00:03:53.740
stages a project passes through from its

00:03:53.800 --> 00:03:56.200
initial idea to completion.

00:03:56.260 --> 00:03:57.900
It helps the team understand where the

00:03:57.980 --> 00:03:59.660
project is and what needs to happen

00:03:59.760 --> 00:04:00.220
next.

00:04:01.160 --> 00:04:03.180
For Riverside School, a simple example

00:04:03.220 --> 00:04:04.260
has four stages.

00:04:05.220 --> 00:04:07.280
First, identify the need and decide

00:04:07.320 --> 00:04:08.800
whether the project should go ahead.

00:04:09.920 --> 00:04:11.780
Second, plan and design the school.

00:04:12.860 --> 00:04:14.940
Third, carry out the delivery work,

00:04:15.000 --> 00:04:16.930
including construction and the required

00:04:16.980 --> 00:04:17.360
checks.

00:04:18.460 --> 00:04:20.440
Fourth, complete handover and close the

00:04:20.500 --> 00:04:21.000
project.

00:04:22.040 --> 00:04:23.740
Different organisations use different

00:04:23.840 --> 00:04:25.840
stage names, and some stages may

00:04:25.900 --> 00:04:26.420
overlap.

00:04:27.440 --> 00:04:29.040
Monitoring and control take place

00:04:29.050 --> 00:04:29.980
throughout the journey.

00:04:30.930 --> 00:04:32.730
The important idea is that a project

00:04:32.760 --> 00:04:34.630
develops through stages; it does not

00:04:34.640 --> 00:04:36.400
begin and end with the construction work

00:04:36.460 --> 00:04:36.830
alone.

00:04:38.080 --> 00:04:39.770
Scope describes the agreed work and

00:04:39.820 --> 00:04:42.560
deliverables included in the project.

00:04:42.620 --> 00:04:44.810
It also makes the boundaries clear: what

00:04:44.860 --> 00:04:46.920
is included, and what is excluded?

00:04:47.940 --> 00:04:49.740
Imagine the agreed scope for Riverside

00:04:49.800 --> 00:04:52.220
School includes six classrooms, toilets,

00:04:52.460 --> 00:04:54.040
an office and a playground.

00:04:55.060 --> 00:04:56.740
A sports hall is not included.

00:04:57.800 --> 00:04:59.520
If somebody later asks for a sports

00:04:59.560 --> 00:05:01.500
hall, that request changes the agreed

00:05:01.620 --> 00:05:01.900
scope.

00:05:02.940 --> 00:05:04.650
The team needs to assess the effect and

00:05:04.680 --> 00:05:07.080
obtain the required approval.

00:05:07.120 --> 00:05:09.120
Clear scope helps people estimate time,

00:05:09.360 --> 00:05:10.400
cost and resources.

00:05:11.440 --> 00:05:13.470
It also reduces misunderstandings about

00:05:13.540 --> 00:05:14.740
what the finished project should

00:05:14.780 --> 00:05:15.440
contain.

00:05:16.360 --> 00:05:18.080
When you hear the word scope, ask a

00:05:18.100 --> 00:05:20.020
simple question: exactly what have we

00:05:20.060 --> 00:05:20.870
agreed to deliver?

00:05:21.900 --> 00:05:23.460
Do not assume that everybody has the

00:05:23.500 --> 00:05:24.680
same picture in mind.

00:05:25.690 --> 00:05:27.820
A deliverable is an identifiable output

00:05:27.840 --> 00:05:29.280
that the project must produce.

00:05:30.340 --> 00:05:31.920
It could be something physical, a

00:05:31.940 --> 00:05:33.940
document, a system or another agreed

00:05:34.000 --> 00:05:34.580
result.

00:05:35.460 --> 00:05:37.200
At Riverside School, a completed

00:05:37.240 --> 00:05:38.640
classroom is a deliverable.

00:05:39.550 --> 00:05:41.540
An approved design drawing can also be a

00:05:41.580 --> 00:05:42.260
deliverable.

00:05:43.180 --> 00:05:45.010
So can the handover pack that explains

00:05:45.040 --> 00:05:46.670
how the building should be operated and

00:05:46.700 --> 00:05:48.300
maintained.

00:05:48.340 --> 00:05:50.000
Deliverables help us describe what

00:05:50.080 --> 00:05:51.900
successful completion looks like.

00:05:52.840 --> 00:05:55.560
Compare the words work and output.

00:05:55.660 --> 00:05:57.740
Installing classroom windows is work.

00:05:58.740 --> 00:06:00.880
The installed, accepted windows are an

00:06:00.940 --> 00:06:01.990
output of that work.

00:06:03.080 --> 00:06:04.700
Later, we will use activities to

00:06:04.740 --> 00:06:06.620
describe the tasks needed to produce

00:06:06.660 --> 00:06:07.360
deliverables.

00:06:08.460 --> 00:06:10.340
For now, remember that a deliverable is

00:06:10.380 --> 00:06:11.990
something the project produces and that

00:06:12.020 --> 00:06:13.880
its required completion or acceptance

00:06:13.900 --> 00:06:16.060
conditions should be clear.

00:06:16.200 --> 00:06:18.420
Stakeholders are people or organisations

00:06:18.460 --> 00:06:20.120
that can influence the project, are

00:06:20.160 --> 00:06:22.240
involved in it, or are affected by its

00:06:22.320 --> 00:06:22.770
outcome.

00:06:23.790 --> 00:06:25.360
They do not all work for the project

00:06:25.420 --> 00:06:26.700
team.

00:06:26.780 --> 00:06:28.460
At Riverside School, the council

00:06:28.520 --> 00:06:30.240
provides funding and direction.

00:06:31.080 --> 00:06:32.900
Teachers need classrooms that support

00:06:32.940 --> 00:06:33.500
teaching.

00:06:34.380 --> 00:06:36.020
The contractor carries out the building

00:06:36.120 --> 00:06:36.440
work.

00:06:37.460 --> 00:06:39.000
Pupils will use the school, and

00:06:39.010 --> 00:06:40.320
neighbours may be affected by

00:06:40.340 --> 00:06:42.940
construction traffic and noise.

00:06:43.060 --> 00:06:46.020
These are all examples of stakeholders.

00:06:46.100 --> 00:06:48.780
Their needs and influence will differ.

00:06:48.820 --> 00:06:50.300
The planner may need information or

00:06:50.320 --> 00:06:51.930
decisions from several of them before

00:06:51.930 --> 00:06:53.390
the schedule can be realistic.

00:06:54.440 --> 00:06:55.800
You do not need a complicated

00:06:55.880 --> 00:06:58.000
stakeholder chart yet.

00:06:58.120 --> 00:07:00.060
Start by asking: who can affect this

00:07:00.100 --> 00:07:02.220
project, who is affected by it, and

00:07:02.280 --> 00:07:03.460
whose input do we need?

00:07:04.440 --> 00:07:06.360
A constraint is a requirement or limit

00:07:06.400 --> 00:07:08.100
within which the project must operate.

00:07:09.160 --> 00:07:11.000
Three familiar project limits concern

00:07:11.080 --> 00:07:12.680
scope, time and cost.

00:07:13.700 --> 00:07:15.440
The required quality must also be

00:07:15.520 --> 00:07:16.060
achieved.

00:07:17.100 --> 00:07:18.960
For our school, scope could mean six

00:07:19.020 --> 00:07:20.700
classrooms and the agreed supporting

00:07:20.740 --> 00:07:22.380
facilities.

00:07:22.440 --> 00:07:24.020
Time could mean being ready for the new

00:07:24.060 --> 00:07:25.680
school year.

00:07:25.740 --> 00:07:27.560
Cost means staying within the authorised

00:07:27.580 --> 00:07:28.980
budget.

00:07:29.020 --> 00:07:31.100
If the client adds two classrooms, the

00:07:31.140 --> 00:07:32.880
team should consider whether more time,

00:07:33.080 --> 00:07:34.640
more money or a different delivery

00:07:34.680 --> 00:07:36.540
approach is needed.

00:07:36.600 --> 00:07:38.520
Changing one part can affect the others.

00:07:39.580 --> 00:07:41.060
It would not be sensible simply to

00:07:41.100 --> 00:07:42.750
promise more work in the same time with

00:07:42.760 --> 00:07:44.330
the same resources without checking.

00:07:45.330 --> 00:07:47.060
Quality requirements still apply.

00:07:48.100 --> 00:07:50.350
Remember: what must we deliver, by when,

00:07:50.580 --> 00:07:51.600
and within what budget?

00:07:52.590 --> 00:07:54.280
These broad project constraints are

00:07:54.340 --> 00:07:55.920
different from the date constraints we

00:07:55.940 --> 00:07:58.600
will introduce in P-six later.

00:07:58.620 --> 00:08:00.700
Resources are the people, equipment and

00:08:00.740 --> 00:08:02.810
materials needed to carry out the work.

00:08:03.900 --> 00:08:05.640
When planning an activity, we need to

00:08:05.680 --> 00:08:07.690
consider what resources it requires and

00:08:07.720 --> 00:08:08.940
whether those resources will be

00:08:09.000 --> 00:08:10.480
available.

00:08:10.540 --> 00:08:12.280
For example, building a wall at

00:08:12.320 --> 00:08:13.920
Riverside School may require a

00:08:13.960 --> 00:08:15.820
bricklaying crew, suitable access

00:08:15.860 --> 00:08:18.660
equipment, bricks and mortar.

00:08:18.740 --> 00:08:20.600
Having materials on site does not help

00:08:20.640 --> 00:08:22.420
if the required people are unavailable.

00:08:23.500 --> 00:08:25.720
Equally, a crew cannot install windows

00:08:25.760 --> 00:08:26.850
that have not arrived.

00:08:27.940 --> 00:08:29.580
Resource availability can therefore

00:08:29.600 --> 00:08:30.920
limit when work can happen.

00:08:31.960 --> 00:08:33.800
We will learn the practical details in

00:08:33.860 --> 00:08:34.300
class.

00:08:35.360 --> 00:08:37.060
At this stage, remember the three

00:08:37.160 --> 00:08:39.540
everyday categories: people, equipment

00:08:39.550 --> 00:08:41.460
and materials.

00:08:41.500 --> 00:08:43.460
Before accepting a planned date, ask

00:08:43.500 --> 00:08:45.120
whether the resources needed to achieve

00:08:45.160 --> 00:08:47.320
it are actually available.

00:08:47.330 --> 00:08:48.930
You now have the basic language.

00:08:49.950 --> 00:08:52.840
A project delivers a particular result.

00:08:52.920 --> 00:08:56.000
A programme coordinates related changes.

00:08:56.140 --> 00:08:58.190
A portfolio brings investments together

00:08:58.260 --> 00:08:59.680
around wider priorities.

00:09:00.670 --> 00:09:02.740
A project moves through a life cycle,

00:09:02.780 --> 00:09:04.560
has a defined scope, produces

00:09:04.580 --> 00:09:06.720
deliverables and involves stakeholders.

00:09:07.780 --> 00:09:09.680
It also needs resources and must work

00:09:09.700 --> 00:09:10.360
within limits.

00:09:11.380 --> 00:09:13.200
Think back to Riverside School: what are

00:09:13.240 --> 00:09:14.960
we delivering, for whom, with what

00:09:15.020 --> 00:09:16.820
resources, and within which limits?

00:09:17.900 --> 00:09:19.360
When you are ready, click the quiz

00:09:19.420 --> 00:09:20.510
button below the video.

00:09:21.540 --> 00:09:23.240
You will have ten minutes to answer ten

00:09:23.300 --> 00:09:26.060
questions and download your results.

00:09:26.180 --> 00:09:27.960
After submitting them, you can continue

00:09:28.000 --> 00:09:28.760
to Lesson Two.